Mason Road Paving to Begin Oct. 15th


Mason Road Paving

On Oct 15th the road reclamation will begin on Mason Rd from Heywood Rd to the N.H. line. During this process emergency & essential  vehicles (buses, postal, and road residents) will have access using caution. This process is estimated to take 4 days.

At the conclusion of the reclamation, paving is scheduled to start on or about the 19th.. Once the paving is started the road will be closed & reopened to traffic by sections. Due to the fact that the pavers haul trucks can’t go into N.H. the paving will start at the N.H. line and progress towards town. As a result loaded trucks will be backing in while empties are coming out. Unfortunately some residents may be inconvenienced but please, try and work with us and we’ll get the project finished as soon as possible. I apologize in advance for any difficulties to residents that this project may create. Sincerely; Bill Davis – Supt.  